Transformer radiator powder coating: a plant in Lu’an, Anhui
A radiator manufacturer in Lu’an, Anhui supplies welded panel radiators to new-energy transformer builders. They needed their own coating line because outsourced coating was costing them lead time and quality control on fin edges. The project below is the scope we supplied and commissioned.



The parts
Welded panel radiators for oil-immersed and dry-type transformers: flat panels with dense fin stacks, wall thickness 1.2-2.0 mm, heights from roughly 400 mm to 1,600 mm, supplied in mixed batches rather than one size at a time.
What the line had to solve
- Fin edges and the gaps between fins are the hard part – a booth aimed at the flat face leaves thin film inside the stack.
- Mixed heights on one conveyor: a fixed gun height either misses tall panels or wastes powder on short ones.
- Colour changes several times a week for different transformer customers, so booth cleaning time sets the real output.
- Weld oil and dust on incoming panels would show through the powder as pinholes.
How the line is built
- Four-stage pretreatment: degreasing, rinse, conversion coating, rinse, then a dry-off oven – sized for the oil carried on welded panels, not just dust.
- Overhead conveyor with adjustable V-hangers so short and tall radiators can run in the same batch without changing the line.
- Reciprocating gun carriages on both sides, stroke set per panel height, with the gun-to-part distance kept constant by a fixed track offset.
- Quick-clean booth floor and reclaim hopper so a colour change is a cleaning job of tens of minutes, not hours.
- Tunnel oven with a controlled heat-up zone, because thick radiator stacks take longer to reach core temperature than the panel face suggests.
Acceptance and handover
The contract fixed film thickness 60-80 um on flat faces, cross-cut adhesion class 0-1 to ISO 2409, and oven uniformity within +/-5 C measured at three points across the work zone. First-off panels were coated at commissioning and checked against those three numbers before handover, together with a spare-parts list and two days of operator training.
Customer name withheld at the customer’s request. Project reference and measured reports can be shown on request.