Turnkey coating line: what to fix in the contract before you sign
Two suppliers can both say “turnkey” and mean completely different things. One delivers steel to your dock and leaves; the other hands you a line that produces good parts at the agreed rate. The gap between them is rarely equipment quality — it is contract wording. Seven clauses decide whether your project closes on time and on budget.
1. Scope of supply, item by item
A turnkey offer should list every item with model, quantity and make: pretreatment tanks or tunnel, dry-off oven, booth and recovery, curing oven, conveyor, guns and reciprocators, control panel, hoppers, spare hangers. Name the brand and model of the components you care about — guns, burner, PLC, VFD, pneumatic cylinders. A line that says “famous brand electrical” is not a specification.
Then write the exclusion list. Typical exclusions: civil works and foundations, pit and drainage, compressed air piping beyond the header, power cable from your transformer to the control panel, water supply, powder or paint, forklift and crane for unloading, and permits. If it is not written down, it will be argued about on site.
2. Who does what
- Supplier — design drawings, manufacture, factory test, export packing, shipping documents, supervision of erection, commissioning, operator training
- Buyer — foundations built to the supplier drawing, unloading and inland transport, secure storage, local labour and scaffolding, utilities to one agreed point, safety compliance and work permits
Put dates against both sides. A supplier team standing idle because foundations are late is a cost that lands on the buyer, usually as a claim or as a shorter installation window.
3. Installation, commissioning and the calendar
Ask four questions: how many supervisor days are included, who pays flights, visa, hotel, food and local transport, what is the day rate for extra days, and what happens if the site is not ready. A mid-size line commonly needs 20–40 supervisor days for erection and 7–14 for commissioning and training, but the number depends on scope, not on optimism. Fix a start date, a completion date and a delay penalty — 0.5% of contract value per week, capped at 5%, is a common and fair figure.
4. Acceptance test — put the numbers in the contract
Acceptance should be measurable, not a handshake at the end of commissioning. Typical items to define:
- Film thickness within ±10 µm of the agreed target
- Adhesion by cross-cut test (ISO 2409 / ASTM D3359), class 0–1
- Gloss and colour against an approved sample panel
- Curing: substrate reaches the powder’s specified metal temperature, measured by data logger
- Oven temperature uniformity, commonly ±5 °C across the work zone
- Throughput: parts per hour at the agreed hanger pitch
- Salt spray hours for the agreed coating system, if outdoor service is claimed
State who witnesses the test, what instrument is used, and that final payment follows a signed acceptance report. If the line cannot reach the numbers, the remedy and the re-test date belong in the same clause — not in a later negotiation.
5. Warranty, spare parts and service
Warranty should start at commissioning acceptance, not at shipment. Sea freight plus site delay can consume six months of a twelve-month warranty before the line ever runs. Wear parts — filters, belts, gun electrodes, burner nozzles — are normally excluded, so list them with prices.
Demand a spare parts list with part numbers and prices, and agree a starter stock: filter cartridges, electrodes, hanger hooks, one set of critical sensors. For plants far from the supplier, agree remote support terms, a stated response time, and the day rate plus travel basis for an on-site visit. That paragraph is what you will actually rely on in year three.
6. Payment, shipping terms and currency
A common structure is 30% with order, 60–70% before shipment against photos or third-party inspection, and the balance after acceptance. On larger projects, a performance bond or a 5–10% retention held for six to twelve months gives the buyer real leverage.
Agree Incoterms explicitly — FOB port, CIF destination port, or DAP site — and say who clears customs and who pays duty, VAT and port charges. These are normally the buyer’s, but “normally” is not a clause.
7. Documents and training
Deliverables: layout and foundation drawings, electrical schematic and I/O list, operation and maintenance manuals, spare parts catalogue, PLC program backup, commissioning report, signed acceptance report. Training: number of days, number of operators, language, and whether it happens before or after acceptance. A line nobody is trained to run is not yet a working line.
Red flags in a turnkey offer
- A price with no equipment list attached
- “Installation included” with no supervisor days or travel terms
- Warranty starting at shipment instead of commissioning
- No acceptance criteria — only “the line will work well”
- No spare parts prices, only a promise of availability
- Foundation drawings promised after payment, when you must build them first
Frequently asked questions
Is turnkey more expensive than buying the pieces separately?
Sometimes on paper, rarely in total. Separate purchases move interface risk onto you: booth airflow against oven balance, conveyor speed against dwell time, who is responsible for the control panel. A turnkey price includes that risk, and one accountable party is usually cheaper than three.
Who pays import duty and port charges?
Normally the buyer. Agree the Incoterm first, then state who clears customs and who handles the port. Disputes at the port cost more than the duty.
Can we erect the line with our own contractor?
Many buyers do the civil works and steel erection locally, which is sensible. Keep supplier supervision for alignment, airflow balancing and temperature tuning — that is where start-up problems appear, and it is the supervisor’s job, not your contractor’s.